What is the process when laying poly underlayment under a concrete slab?

Study for the General Contractor License (KB2) Exam. Use flashcards and multiple-choice questions, with hints and explanations provided. Prepare effectively for your exam and boost your confidence!

Multiple Choice

What is the process when laying poly underlayment under a concrete slab?

Explanation:
When laying poly underlayment under a concrete slab, it is important to ensure that the edges are overlapped properly to provide an effective moisture barrier. Overlapping the edges by 6 inches is a common industry standard that ensures a secure and continuous barrier against moisture migration from the ground below the slab. This overlap helps to prevent issues related to water infiltration, such as mold growth or slab deterioration, which can arise if gaps or seams are present in the moisture barrier. A 6-inch overlap strikes a balance between being substantial enough to secure the moisture barrier while also being manageable for installation, making it the recommended practice for this process.

When laying poly underlayment under a concrete slab, it is important to ensure that the edges are overlapped properly to provide an effective moisture barrier. Overlapping the edges by 6 inches is a common industry standard that ensures a secure and continuous barrier against moisture migration from the ground below the slab. This overlap helps to prevent issues related to water infiltration, such as mold growth or slab deterioration, which can arise if gaps or seams are present in the moisture barrier. A 6-inch overlap strikes a balance between being substantial enough to secure the moisture barrier while also being manageable for installation, making it the recommended practice for this process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy